Development and conversion of the PACK PLUS production plant in order to add a new production building and a staff, office and technical building together with a partial change in the use of these buildings


Investor: Pack Plus Sp. z o.o. Sp. k.

Address:  ul. Chopina 39
             34 -100 Wadowice
 
Surface area: A hall erected in two phases: 2380 m2 and 1798 m2 together with an office of 1584 m2
 
Scope of works: A production hall erected in two phases and a building constructed in two parts – two floor, staff and office turn-key building. Demolition of the existing buildings which collide with the newly erected ones. Management of the plant’s surroundings and the construction of a new fire water tank.
 
Construction period: From December 2016 to October 2017 (Q4)