High rack warehouse extension
The name of the contract: Extension of a high rack warehouse together with the development of the area and the necessary technical infrastructure in Tychy:
Contracting entity: M-LOGISTIC Sp. z o. o.
Construction period: 05.01.2015 – 30.12. 2015
Scope of works: General contracting
Investment description:
The planned investment consists of an extension of a high rack warehouse by 5600 m2, expansion of the lorry and car parking lot and reconstruction of external networks.
Construction of the warehouse: The main construction consists of steel warehouse racks installed on reinforced concrete, monolith concrete slab to which the casing of the hall will be bolted – a roof in the ASTRON technology and walls made of sandwich panels.
Contracting entity: M-LOGISTIC Sp. z o. o.
Construction period: 05.01.2015 – 30.12. 2015
Scope of works: General contracting
Investment description:
The planned investment consists of an extension of a high rack warehouse by 5600 m2, expansion of the lorry and car parking lot and reconstruction of external networks.
Construction of the warehouse: The main construction consists of steel warehouse racks installed on reinforced concrete, monolith concrete slab to which the casing of the hall will be bolted – a roof in the ASTRON technology and walls made of sandwich panels.